In a recent webinar, I received this question form one of our participants...

Jason
How often should my maintenance department level our injection molding machines?

My Response
It depends... but typically larger machines should be levelled every 6 months. The smaller machines tend to be more stable and rigid, requiring levelling every 12 months.

What is even more important is the fact that you need to measure any machine that is new to your facility every 3 months for the first year. Many molders assume that newer machines require less attention, but it may take up to a year for the machine to settle in.

Additional Thoughts
Keep in mind, you should always level the machine by placing the level on the tie bars. Although bubble levels can be used, a laser level is significantly more effective at measuring the levelness of the machine. Clean off the tie bar before measuring and use a grooved level so that it properly rests on the tie bar.

-Andy

No TrackBacks

TrackBack URL: http://blog.traininteractive.com/mt/mt-tb.cgi/14

Leave a comment

About this Entry

This page contains a single entry by Andy Routsis published on August 11, 2009 12:00 PM.

Example: Calculating Clamp Tonnage was the previous entry in this blog.

Processing With Flame Retardant Polymers is the next entry in this blog.

Find recent content on the main index or look in the archives to find all content.